THE CITY OF FREDERICK, MARYLAND – CAPITAL IMPROVEMENTS PROGRAM

FOR THE FISCAL YEARS     2004-2009                      

PROJECT MANAGER – Facilities Manager    DPW Building A Roof Replacement   120002

 

 

 

 

SCOPE

 

Replace 33,526 sq-ft roof at DPW Building "A" and warp existing masonry cap with aluminum sheeting.

 

JUSTIFICATION

 

The existing roof carries a 10-year warranty and was installed in May, 1991.  The roof will be replaced with a 60-mil (vice existing 45-mil) Firestone EPDM rubber membrane roof.  It will be mechanically adhered (note:  present roof is not) and installation shall include isothermal board.

 

This replacement and repair will eliminate the leaks that are causing interior leaks and prevent the further deterioration of the masonry caps.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

THE CITY OF FREDERICK, MARYLAND – CAPITAL IMPROVEMENTS PROGRAM

FOR THE FISCAL YEARS     2004-2009                      

PROJECT MANAGER – Facilities Manager                                 Relocate Storage Building to DPW   120003

 

 

 

SCOPE

 

This project involves erecting a used, approximately 43,000 SF steel building at the DPW for use as a vehicle, equipment and material storage building.  This building is located at 251 Bailes Lane, and is scheduled to be demolished as part of the Obstruction Removal Program for the Frederick Municipal Airport.  The plan for this building is to dismantle the building using FAA funds, and re-erect the building at the DPW Yard on concrete foundations.

This project includes dismantling, hauling, and re-erecting the structure at the nearby Frederick DPW complex. Also included is the construction of a new 6-inch concrete floor slab at the new site, and saw cutting and pouring concrete footers and piers to support the building's frame structure.

 

1. Dismantle existing building - 43,000 sf @ $3.50/sf                                                                                                                                   $150,500

2. Load and haul materials to new site/dispose of non-reusable materials (Lump sum)                                                                              $8,500

3. Construct new concrete footers and piers (Lump sum)(including saw-cutting exist. asphalt,  excavation, and repair)        $50,000

4. Re-erect structure - 43,200sf @ $2.50/sf                                                                                                                                                $108,000

5. Contingency for new hardware, worn/damaged sheet metal, and utility connections                                                                          $75,000

6. Paint building – 21,000 sf @ $1.50/sf                                                                                                                                                               $30,000

 

TOTAL (including Items 1 through 6)                                                                                                                                                                        $422,000

 

* Items 1 and 2 of this estimate could be covered by FAA funds obtained by the Frederick Municipal Airport as part of their Obstruction Removal Program.  If these funds are obtained from the FAA, the total costs for this CIP project would be $293,000, including engineering costs.

 

JUSTIFICATION

 

This building is in good condition, but needs to be removed per FAA requirements for flight path obstructions.  By re-erecting this building at DPW, there would be significant cost savings over purchasing and erecting a new building.  The City’s cost for this work will be about $6.50 per square foot versus $9 – 10 per square foot for the purchase and construction of a new building   The building materials would be recycled into the new building, eliminating the cost of disposal at the landfill.

 

Erection of this building at DPW would provide an indoor storage area for all DPW vehicles, where most are now stored outside.  If the vehicles and equipment are stored inside, the effects of weather would be less and the vehicles will last longer.  It would also provide a safer environment for employees to perform minor maintenance on vehicles.  During snow removal operations, the salt spreaders and plows could be installed on the trucks without having ice and snow accumulated on them, which creates a safety hazard to the employees.

 

THE CITY OF FREDERICK, MARYLAND – CAPITAL IMPROVEMENTS PROGRAM

FOR THE FISCAL YEARS     2004-2009                      

PROJECT MANAGER – Director of Planning                                                 City-wide Traffic Study     130002

 

 

SCOPE

 

The project involves the following tasks: 

Task 1 & 1A – Prepare Scope of Work: Develop a detail scope of work for the entire project after reviewing all existing data sources, and interviewing all stakeholders. 

Tasks 2 & 2A – Data Collection:  This task involves traffic count collection for 120+ intersections and 70+ miles of roadways within the City.  Inventory of City streets will involve – number of lanes, road widths, parking, speed limits, curbed areas, bus stops, school zones, etc.

Task 3 – Develop and Validate Synchro Network:  The RBA Group will develop a Synchro network for the study area intersections and roadways. 

Task 4 – Evaluate Existing Operations: The RBA Group will perform capacity analysis for all study area intersections and evaluate network signal operation, using Synchro.

Task 5 – Evaluate Ultimate Land Use/Transportation Plan:  Working with the Planning Department, The RBA Group will develop a long-range travel demand model of the City’s future development based on the Comprehensive Plan.

Task 5A – Special Area Studies:  Three mutually agreed upon sub-area transportation studies will be conducted by The RBA Group to evaluate existing conditions and make improvement recommendations.

Task 6 – Develop Staging Plan:  Originally planned as an evaluation of phased improvements, this task has been combined with Task 5.

Task 7 – Prepare Guidelines:  The RBA Group will develop guidelines for the submission of traffic impact studies in support of development proposals.

Task 8 – Final Report:  Originally planned as formal report, this task has been combined with Task 5.

Task 9 – Future Updates:  The RBA Group will provide training to City personnel in the use of Synchro/SimTraffic so that the model can be constantly updated. 

Task 10 – Meetings/Hearings:  This task covers the various meetings with City staff, elected officials and the public needed to complete the project.

 

JUSTIFICATION

 

As a result of the City of Frederick’s rapid growth and its strategic location at the confluence of Interstates 70 and 270, the increasing traffic load has been placed on the City’s road system.  The City has historically not monitored its traffic conditions and, therefore, has not been able to plan for the needed road improvements to address the traffic congestion that has been experienced.  The Mayor and Board of Aldermen acknowledged the need to comprehensively evaluate the City’s road system by approving as part of the FY 2000 Capital Improvement Budget a $300,000 project to do a Citywide Traffic Study.  The project was reaffirmed as part of the FY 2001 Budget with an additional $150,000 allocated to cover other components of the project not originally anticipated when the project was first established.  The project is to be completed in fall of 2003.

 

 

 

THE CITY OF FREDERICK, MARYLAND – CAPITAL IMPROVEMENTS PROGRAM

FOR THE FISCAL YEARS     2004-2009                      

PROJECT MANAGER – Facilities Manager                                                           Municipal Facilities     210005

 

 

SCOPE

 

Project A -  City to perform study of feasibility and cost to use the Masonic Lodge on Church Street for various City Administrative Offices.  Feasibility Study of Masonic Lodge will include renovating building and updating operating systems as well as necessary improvements to meet current life safety and ADA codes.  Second part of Study will include “stacking plan” to determine optimum departmental placement per adjacency and space requirements. To be completed by end of FY2003.

 

Project B - Team to be formed to study and recommend new location for Frederick City Police HQ.  Team to verify projected space needs, staffing, and operational requirements. Will also require review of other existing Police Department facilities and functions.  Potential sites will be reviewed and preliminary budget prepared. End product will be recommendation to Mayor on location and cost for new facility.  Recommendation to be included in FY2005 CIP Budget in January 2004.

 

Project C - Acquisition and construction of new City Administrative Offices.  Final schedule to be determined upon completion of Project A above. $3M in budget to acquire and renovate space.

 

 

 

JUSTIFICATION

 

City has outgrown existing space for municipal services in City Hall, 7th Street, and the Court House.  Also various departments are not strategically located.  Project required to meet demands of operating City government.

 

 

 

 

 

 

 

 

 

 

THE CITY OF FREDERICK, MARYLAND – CAPITAL IMPROVEMENTS PROGRAM

FOR THE FISCAL YEARS     2004-2009                      

PROJECT MANAGER – Facilities Manager                                    Police Academy Training Room     210007

 

 

SCOPE

 

City to erect a 3,700 sq. ft. pre-engineered building at the Linganore Firing Range.  Building will house multipurpose training space with room divider, restrooms, and storage areas.  Project will also include all utility tie-ins.  The building will be constructed using steel framing on a concreter foundation with galvanized steel sheeting for roof and sidewalls.  The interior will be insulated and include heating and air conditioning. Project was bid as a design-build and will be engineered by the selected contractor.   Equipment for Interior fit-out will be part of the Expense Budget.

 

JUSTIFICATION

 

The Frederick Police Department Training Facility was constructed in 1981 at which time the facility served approximately 80 officers.  Since that time, the Police Department has grown to 128 officers and 60 civilians, auxiliary, explorers, chaplains, volunteers, etc.  Over the past two years, the original training room has been expanded by removing two offices and renovating the garage area into office space.  City Police Department still has insufficient space for  storage, classroom, and physical training at its Linganore Firing Range and requires additional space.  Further expansion of this 22-year-old building would be cost prohibited.  Training facilities are also shared on contract basis by other Police departments including the FBI and other federal agencies.  Assistance from outside agencies offset costs and helps create up-to-date training facilities for City Police employees.  The construction of a new building also allows for multiple activities to be scheduled at the same time.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

THE CITY OF FREDERICK, MARYLAND – CAPITAL IMPROVEMENTS PROGRAM

FOR THE FISCAL YEARS     2004-2009                       

PROJECT MANAGER – Chief Public Safety Officer                       Mobile Data Interface     210008

 

SCOPE

 

Currently the police department utilizes a legacy system owned by Frederick County for call dispatching and storage of statistical information.    This computer aided dispatch / records management system (CAD/RMS) has exceeded its usefulness.

 

Frederick County Government tentatively will be awarding a contract to one of seven competing vendors for a new CAD/RMS during this fiscal year, which will be utilized by all major police agencies within the county.

 

This request is to create a new software interface between the new CAD/RMS and our existing in-vehicle mobile data computer network

 

 

JUSTIFICATION

 

The replacement of the existing system with a new state of the art CAD/RMS provides the Department an exciting opportunity to fully integrate our existing in-vehicle mobile data computer network with the new CAD/RMS, moving closer to a “paperless” environment.

 

A software interface between these two critical systems would permit the immediate transfer of electronic police reports, completed in the field, directly into the records management system without additional data entry from support personnel as is today’s practice. 

 

Additional benefits would include:

¨ Digital dispatch of field deployed officers replacing voice transmissions.

¨ Allow responding units to send status updates by computer.

¨ Allow field units immediate access to local department databases.

 

 

 

 

 

 

 

THE CITY OF FREDERICK, MARYLAND – CAPITAL IMPROVEMENTS PROGRAM

FOR THE FISCAL YEARS     2004-2009                      

PROJECT MANAGER – Director of Engineering            East Street Extension-Phase II     310133

 

 

SCOPE

 

The City entered into a Memorandum of Understanding with the State Highway Administration (SHA) to match funds (50%) for the design engineering for the East Street extension from South Street to Walser Drive.  All work is to be done by SHA or their consultant.  The project management is controlled by SHA.  No tasks have been defined for the City’s participation.

 

JUSTIFICATION

 

This section of road is designated a Major Arterial on the 1995 Comprehensive Plan.

County #1 priority of SHA secondary projects.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

THE CITY OF FREDERICK, MARYLAND – CAPITAL IMPROVEMENTS PROGRAM

FOR THE FISCAL YEARS     2004-2009                      

PROJECT MANAGER – Director of Engineering                          Monocacy Blvd. – North Section     310302

 

 

SCOPE

 

Phase 1 – Design and construct 4-lane roadway from the existing Gas House Pike bridge at the Monocacy River to a point past the entrance to the CSR site approximately 700 feet south of the Monocacy River.

 

Deliverables:

·         Engineering studies

·         Detailed design drawings and specifications

·         Acquisition of required permits for construction, inspection reports and project management

·         Grading of the roadway including import of fill and disposal of unsuitable materials

·         Sediment control and storm water management

·         Storm drainage, water and sanitary sewer including a sewage pumping station

·         Installation of conduit for utilities (electric, phone, cable and gas)

·         Installation of off-site sanitary sewer across the Monocacy River to existing City sewer line on the west side of the Monocacy River

·         Installation of curbs, gutters, sidewalks and placement of asphalt

 

Phase 2 – Design and construct 4-lane roadway from the beginning of Phase 1 at the point past the entrance to the CSR site approximately 700 feet south of the Monocacy River to the existing Monocacy Blvd. At Laurel Wood Way, including a bridge spanning the Monocacy River.

 

Deliverables:

·         Detailed design drawings and specifications including those for a 674 foot bridge across the Monocacy River

·         Acquisition of required permits for construction, inspection reports and project management

·         Grading of the roadway including import of fill and disposal of unsuitable materials

·         Sediment control and storm water management

·         Storm drainage, water and sanitary sewer including a sewage pumping station

·         Installation of conduit for utilities (electric, phone, cable and gas)

·         Installation of off-site sanitary sewer across the Monocacy River to existing City sewer line on the west side of the Monocacy River

·         Installation of curbs, gutters, sidewalks and placement of asphalt

 

JUSTIFICATION

 

            The project is included in the 1995 Comprehensive Plan, the Frederick County Region Plan (Jan 92) and has been determined to be a number one priority of the City.

 

THE CITY OF FREDERICK, MARYLAND – CAPITAL IMPROVEMENTS PROGRAM

FOR THE FISCAL YEARS     2004-2009                       

PROJECT MANAGER – Director of Engineering               Monocacy Blvd.-Central Section-Ph. 1     310303

 

 

SCOPE

 

This phase of the project will include the design of approximately 4300 linear feet of Gas House Pike from the existing intersection at Monocacy Blvd. (north of the Monocacy River) to the eastern City limit.  Improvements shall include widening the roadway to a four lane closed section (11 foot wide lanes, 16 foot median), the design of a relocated entrance to the Clustered Spires Golf Course, an expansion of the existing parking lot, and intersection designs for the future construction of Wireless Court and Digital Way. 

 

The scope of work includes, but is not limited to, the following plans and services:

 

·                     Control and property (boundary) surveys.

·                     Right of way plats and utility easements.

·                     Geotechnical investigations and recommendations as appropriate.

·                     Flood plain analysis and permitting.

·                     Wetland delineation and permitting.

·                     Utility relocation plans.

·                     Structural engineering, as necessary

·                     Roadway improvement and demolition plans, specification and construction cost estimates.

·                     Water, sewer and storm drain plans.

·                     Storm water management design.

·                     Traffic control plans.

·                     Grading and sediment control plans.

·                    Street tree, sidewalk and street lighting plans.

 

JUSTIFICATION

 

The project is included in the 1995 Comprehensive Plan, the Frederick County Region Plan (Jan 92) and has been determined to be a number one priority of the City.

 

 

 

THE CITY OF FREDERICK, MARYLAND – CAPITAL IMPROVEMENTS PROGRAM

FOR THE FISCAL YEARS     2004-2009                       

PROJECT MANAGER – Director of Engineering    Monocacy Blvd.-Central Section-Ph. II    310304

                                                                                             

 

 

SCOPE

 

This phase of the project will begin with a study to determine overall project requirements of the following entities:

 

Approximately 4050 linear feet of roadway from Hughes Ford Road to Gas House Pike consisting of a four lane closed section (11 foot wide lanes, 16 foot median).  The design will include a structural crossing of Carroll Creek.  Also included is a new two-lane open section access drive to the City of Frederick WWTP.

 

Determine the appropriate configuration of the intersection of Monocacy Boulevard and Gas House Pike.  From the intersection, Monocacy Blvd. will follow existing Gas House Pike approximately 3000 linear feet to the Gas House Pike Bridge.  This portion of the roadway shall be designed as a limited access four lane closed section (11 foot wide, 6 foot median).  A retaining wall designed to withstand the scour velocities from Carroll Creek must be included to support the roadway.  The alignment shall be designed to coordinate with the Phase 3 Bridge replacement.  Also included will be a study of all adjacent storm drainage systems and outfalls and stabilization issues addressed.

 

Also included is the extension of existing Schifferstadt Blvd. approximately 2050 linear feet to the location of the proposed Gas House Pike/Monocacy Blvd. intersection.  This roadway will be a four lane closed section (11 foot wide lanes and 7 foot median). 

 

Design and construction of a four-lane bridge designed to eliminate bridge piers within the waterway and the demolition of the existing concrete bridge.  The location of the new bridge shall be determined in coordination with the Phase 2 roadway design, and with consideration of the existing intersection of Monocacy Blvd. and Gas House Pike.  The design will include connection of the bridge with the existing roadway to the north and the Phase 2 construction, including both horizontal and vertical alignments.

 

Improvements to approximately 4500 linear feet of existing Gas House Pike.  The typical section will be a four lane closed section with 11 foot wide lanes and no median.  Improvements also include designs for the completion of the earthen levee system along the northern side of Carroll Creek.

 

The scope of work includes, but is not limited to, the following plans and services: Control and property (boundary) surveys, right of way plats and utility easements, geotechnical investigations and recommendations, flood plain analysis and permitting, wetland delineation and permitting, utility relocation plans, structural engineering, roadway improvement and demolition plans, specification and construction cost estimates, water, sewer and storm drain plans, storm water management design, traffic control plans, grading and sediment control plans and street tree, sidewalk and street lighting plans.

 

JUSTIFICATION

 

The project is included in the 1995 Comprehensive Plan, the Frederick County Region Plan (Jan 92) and has been determined to be a number one priority of the City.

 

 

 

THE CITY OF FREDERICK, MARYLAND – CAPITAL IMPROVEMENTS PROGRAM

FOR THE FISCAL YEARS     2004-2009                      

PROJECT MANAGER – Director of Engineering                        Opossumtown Pike Realignment      320002

                                                                                    

 

 

SCOPE

 

This project includes improvement of the eastern half of Opossumtown Pike from Sta. 31+90 to Sta. 41+30 (Centerline of the Intersection of McClellan Drive), including improving vertical alignment.  The developer of North Crossing and Clover Ridge will bear the expense of the remainder of the improvement adjacent to their respective frontage between Christopher’s Crossing and McClellan Drive.  The design in currently under way by the developer, and the project is anticipated to be developer built.

 

Deliverables Associated with this project:

· Improvement plans

· Construction of approximately 940 linear feet of two lanes of a 4-lane undivided minor arterial street. (Developer is responsible for remaining two lanes.)

 

JUSTIFICATION

 

This roadway is indicated in the Comprehensive Plan as a minor arterial.  Current widening was done during the construction of Willow Brook, when Opossumtown Pike was a County road, and was not constructed to City standards.  In addition, vertical alignment of the road needs improvement.

 

 

 

 

 

 

 

 

 

 

 

 

THE CITY OF FREDERICK, MARYLAND – CAPITAL IMPROVEMENTS PROGRAM

FOR THE FISCAL YEARS     2004-2009                      

PROJECT MANAGER – Director of Engineering                       Shookstown Road Improvements      320004

                                                                                     

 

 

SCOPE

 

Reconstruct 1400 linear feet of a 2-lane Shookstown Road between Willowdale Drive and Lake Coventry to a 4-lane minor arterial road including the installation of water and sewer mains.

 

JUSTIFICATION

 

In 2001 the City collected performance bonds when a developer failed to complete work in the Lake Coventry subdivision. The City initiated this CIP project to complete the work in Shookstown Road which was required to bring service to the Waverly View subdivision.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

THE CITY OF FREDERICK, MARYLAND – CAPITAL IMPROVEMENTS PROGRAM

FOR THE FISCAL YEARS     2004-2009                      

PROJECT MANAGER – Director of Engineering        Opossumtown Pk./TJ Dr. Intersection Imps.   320007

                                                                                             

 

 

SCOPE

 

            This project includes intersection improvements at the named intersection to improve traffic flow.  This project include the extension of the left and right turn lanes on northbound Opossumtown Pike, which will include the removal of existing curb and gutter and sidewalk, removal of the existing grass and concrete median, relocation of the existing streetlight poles, constructing new curb and gutter and sidewalk, and the construction of new asphalt pavement, new pavement markings and improvements to the traffic signal. 

 

Deliverables:

Construction of additional lanes and geometric improvements

 

JUSTIFICATION

 

            This project is required to improve traffic flow at this intersection.  The existing left and right turn lanes are inadequate to hold the turning traffic, which backs up into the through lanes, causing extended traffic backups.  By extending the turn lanes, the turning traffic will be able to stack in these lanes, opening up the through lanes for other vehicles to stack or travel while the left turn lane is stopped.  This will also minimize weaving movements of traffic between the two through lanes, which will minimize accidents.

 

 

 

 

 

 

 

 

 

 

 

THE CITY OF FREDERICK, MARYLAND – CAPITAL IMPROVEMENTS PROGRAM

FOR THE FISCAL YEARS     2004-2009                      

PROJECT MANAGER – Director of Engineering     E. Patrick/Monocacy Blvd. Intersection Imps.   320008

                                                                                    

 

 

SCOPE

 

This project includes intersection improvements at the named intersection to improve traffic flow.  This project include the addition of right turn lanes at the northwest, northeast, and southwest corners, which will include the removal of existing curb and gutter and sidewalk, constructing new curb and gutter and sidewalk, and the construction of new asphalt pavement, new pavement markings, improvements to the traffic signal, and relocation of a fire hydrant. 

 

A Traffic Study and Right-of-way acquisition will also be required.

 

Deliverables:

· Traffic Study

· Improvement Plans

· Construction of additional lanes and geometric improvements

 

JUSTIFICATION

 

This project is required to improve traffic flow at this intersection.  Currently at each of these corners there is a shared through/right turn lane.  Because of the split-phasing of the signal, traffic builds up in these lanes and creates delays.  By adding right turn lanes at each of these corners, vehicles can make right turns on red, and lessen the backups.  By adding the right turn lanes, additional turning radius will be added to each corner to allow tractor trailers to better negotiate this intersection without entering adjacent lanes or running up on the sidewalks and causing damage to City facilities.

 

 

 

 

 

 

 

 

THE CITY OF FREDERICK, MARYLAND – CAPITAL IMPROVEMENTS PROGRAM

FOR THE FISCAL YEARS     2004-2009                      

PROJECT MANAGER – Director of Engineering                      Rosemont Avenue Traffic Calming     320011

                                                                                   

 

SCOPE

 

To design and construct a traffic calming device along Rosemont Avenue just east of Route 15 to just beyond the entrance of Hood College to moderate traffic for pedestrians/cyclist crossing the wide roadway to Baker Park to not exceed the approved budget.

 

JUSTIFICATION

 

 

To potentially slow down the traffic along Rosemont Avenue and improve the safety for pedestrians/cyclists crossing Rosemont Avenue at the crosswalk.

 

Numerous complaints by neighborhood.