East Church Street Reconstruction Project Update
Frederick, Md. --- The City of Frederick is reconstructing East Church Street.
F.O. Day’s subcontractor will continue installing granite curb and gutter by Winchester Hall heading to Carroll Street. On Wednesday June 1, 2005, F.O. Day expects to have all granite curbs and gutter set, plus binder asphalt installed as well. Department of public works will start working on the sidewalk on the south side.

F.O. Day has installed the last sewer manhole and the 8" sewerline main has been installed. The sewer house connection on the North side of East Church will all be in service at this time.

F.O. Day has started the sewer house connections on the south side of East Church Street. The south side sewer house connection will take approximately 30 days, because it will take at least one and half days to complete one sewer house connection.
For any questions or concerns please contact Paul Lee, P.E., P.Eng., director of engineering, at plee@cityoffrederick.com <mailto:plee@cityoffrederick.com> or 301-600-1405.


 





 

 

 

 

 


 

 


 

 

 