East Church Street Reconstruction Project Update


Frederick, Md. --- The City of Frederick is reconstructing East Church Street. This past week very little work was accomplished due to the rain.

The week to come work on the water main should resume, Monday, October 25. Work will likely consist of installing the tapping sleeve, tapping, charging, sanitizing and testing the pipe. Installation of house connections will begin when bacteriological tests of the pipe come back clean.

For more additional information contact, Alice A. Miller, P.E, Assistant City Engineer, at
301.600.1438


 



 

 

 