PRELIMINARY WELLFIELD DEVELOPMENT WORK TO BEGIN IN JUNE
IN TWO CITY DEVELOPMENTS
Frederick,
Md. --- The City of Frederick will begin work in two
neighborhoods in early June in support of the Citys
Water NOW Team initiative to increase water supplies
for the City of Frederick. Residents in the Fredericktowne
Village and Riverwalk Park areas will notice City
Department of Public Works crews beginning to lay
pipeline as early as Tuesday, June 1. The project
schedule calls for initial pre-construction work to
begin on the park site on or about June 1, and to
be complete within 120 days, or approximately October
1, including final cleanup of the site. Prior to commencement
of pre-construction work, engineers, surveyors and
consultants may be seen walking in the park performing
prepatory tasks.
The
Citys goals include testing and redevelopment
of two existing municipal water supply wells in these
parks. Well #3 is located between the two baseball
fields approximately 550 feet east of Schifferstadt
Boulevard, while Well #7 is located approximately
600 feet west of Schifferstadt Boulevard.
Please note the elements of work, which will take
place in these areas throughout the next 120 days:
Survey
and stakeout of temporary water piping in the park
PLACEMENT by the Department of Public Works of temporary
water piping in the park
Drilling and installation of monitoring wells around
existing Well #3 and Well #7
Drilling Well #7 to a larger diameter, and installation
of permanent well casing
Installation of temporary well pumps
Fencing of the two well sites for security and safety
reasons
Conducting continuous pump testing of the wells for
a period of approximately ten weeks
Removal of equipment, piping and cleanup of the site.
Area
residents can expect to see engineers and contractors
at the two well sites and at the Monocacy River on
a daily basis, including evening and nighttime hours.
During a portion of the testing program, personnel
will be required on site 24 hours a day. Once redrilling
of Well #7 has been completed, both well sites will
be fenced for security and public safety purposes.
Temporary
piping will be laid on the ground, to safely convey
the water generated during well development for proper
discharge and disposal to the Monocacy River. To power
the pumps, portable generators will be used throughout
the testing period. In order to minimize noise levels,
the City will be using "hospital grade"
silencers and acoustical baffling will be added to
absorb sound.
The
City's existing sinkhole monitoring program will be
intensified in Fredericktowne Village Park during
the well testing program, under the direction of the
Engineering Department. As is standard City policy,
the Department of Public Works will immediately respond
to sinkhole reports, assess and repair. Before pumping
begins at either Well #3 and/or #7, the City will
have a Sinkhole Liability Plan in place. The director
of budget and purchasing anticipates presenting a
Sinkhole Liability Plan at the June 3rd Mayor and
Board of Aldermen Public Meeting. The plan will consist
of self-insurance and or other secondary forms of
coverage in addition to the current coverage available
to the City. The plan is to ensure that the City has
in place a plan to enable it to "do the right
thing" if any damage is caused by the operation
of these wells. Currently, the City does have coverage
in place that would allow for recovery under circumstances
where the damage was due to the negligent operations
only. The new plan will ensure recovery due to causation
and not just due to negligence.
The
project has been planned and designed to minimize
any inconvenience to the public during the well testing.
The drilling and testing program will not interfere
with use of the baseball fields in the park. Once
testing is complete, the contractor and the Department
of Public Works will remove all equipment and temporary
piping, and restore the well sites to their previous
condition. If the pumping tests are successful, the
City will return to the sites in early 2005 to install
permanent well pumps and electrical controls.
For
additional information please contact Tom Pellegrino,
CIP Project Manager, at 301-600-1313.