RUNWAY
5/23 REHABILITATION PROJECT UPDATE
The
Phase V portion of the Runway 5/23 project was shut
down last November 21, 2003 to enable the Airport to
have the runway available during the winter and early
spring months. We made the decision to wait until June
2004 to re-start Phase V to take advantage of longer
day light hours and consistently warmer temperatures,
which are more favorable to asphalt paving operations.
Also, April and May usually are wetter periods, which
stop pavement work.
We
plan to re-start the Runway 5/23 Rehabilitation project
on Monday, June 7, 2004. The runway will be officially
NOTAMED closed at 0900 hours on June 7, 2004 until further
notice. The expected duration of the runway closure
for rehabilitation work is July 28, 2004 or weather
permitting sooner. Runway 12/30 (3,600 X 75)
will remain open and operational during the construction
period. Any exceptions will be NOTAMED accordingly.
Those tenants and operators of jet powered aircraft
who cannot use Runway 12/30 during the 5/23 closure
period should plan to move their aircraft out of the
Airport before 0900 on June 7, 2004.
FAA
will NOTAM the ILS out of service during the construction.
Meanwhile, we will continue to complete the final items
on FAAs punch list to satisfy the various FAA
Airways Facility Divisions.
If
you have any questions, please call Charlie Abell, Airport
Manager, at 301-846-2201.
|