UPDATE ON THE PATRICK AND COURT STREET WATER MAIN REPLACEMENT PROJECT

Frederick, Md. --- The City of Frederick will begin a major water main replacement project late this summer that will impact travelers in the downtown. The purpose of this project is to replace deteriorated 4”, 6” and 8” mains along West Patrick and South Court Streets with new 8” and 16” pipes. The overall goals of this project are to improve water pressure for new construction in the downtown district, improve water quality, and provide the ability to convey larger quantities of water from the Potomac River when that project comes online.

The following is a summary of what travelers and pedestrians should expect in the
months to come:
Construction activity will begin on or around September 1st.
Expect one lane of vehicular traffic Monday - Friday, 7 a.m. - 8 p.m., on West Patrick Street from Court Street to Bentz Street. Weekend work is currently not planned or scheduled; however this could change if emergencies arise.
Expect construction equipment to operate during the 13-hour workday timeframe. This equipment will result in noise, light dust and activity.
Pedestrian traffic will be maintained on both sides of the streets at all times.
Businesses and residences may experience short interruptions in water service, up to one hour, while new water mains are tied in.
There will be visible temporary water mains in and/or on street gutters.
Water users may experience possible sediment visible in water supply during main changeovers. If this occurs, simply run faucets to clear.
Work on West Patrick Street will begin at Court Street and work towards Bentz Street. This phase will be known as Phase 1a and it will last approximately six weeks.
Depending on the duration of work on Phase 1a, the City may begin work on Court Street. This work, from Patrick Street toward Carroll Creek, will be known as Phase 1b. The City expects this phase to last approximately three weeks.
In any event this project will be finished for the winter during the first week of November 2004 and resume in Spring 2005.

For additional information please contact the City of Frederick’s Project Manager, Marc
Stachowski, 301-600-1440 or 600-1169, or via email at stachowski@cityoffrederick.com.















 

 