NEWS RELEASE
Mayor: Jennifer P. Dougherty
CONTACT: Andrew
McGilvray, Street Division Chief, (301) 600-1172
FOR IMMEDIATE RELEASE: Tuesday, June 11, 2002
The City of Frederick Department of Public Works will be repaving the streets on the attached list this summer. This work may involve milling of all or part of the existing asphalt, and the placement of a new overlay of hot mix asphalt. Prior to this work, The City DPW may be replacing curb & gutter, and repairing the existing roadway.
Attached
is the proposed schedule for the milling and paving work, as proposed by our
contractor. This schedule may vary,
depending on weather and other unforeseen circumstances. Please consult this schedule to determine when
the work will be performed on each street.
During this work, no parking will be allowed on the scheduled day for
each street, in the area of work. The
City will put up No Parking signs prior to the days scheduled for each
street. Residents and motorists are
requested to obey these signs to avoid causing any delays to our contractor,
and to avoid having your vehicle towed.
Thank
you in advance for your cooperation.
(Over)
THE CITY OF FREDERICK
2002 STREET RESURFACING
PROJECT
PROJECT SCHEDULE
|
STREET |
FROM |
TO |
START
WORK |
END
WORK |
|
Airport Dr. East |
Bowman’s Farm Rd. |
DPW Entrance |
June 12 |
June 17 |
|
Christopher Crossing |
Whittier Dr. (East) |
900’ West |
June 18 |
June 19 |
|
Lakeside Dr. |
Wetherburne Way |
Wren Alley |
June 18 |
June 19 |
|
Wetherburne Way |
Whittier Dr. |
Wetherburne Way |
June 18 |
June 19 |
|
Key Pkwy 1 |
Bel Aire Lane |
Old Camp Rd |
June 20 |
June 25 |
|
Taney Ave. |
West 7th St. |
Thomas Johnson Dr. |
June 26 |
July 1 |
|
Sagner Ave. |
Maryland Ave. |
S. Wisner St. |
July 2 |
July 8 |
|
S. Wisner St. |
Sagner Ave. |
E. South St. |
July 2 |
July 8 |
|
S. Water St. |
E. South St. |
B&O Ave. |
July 2 |
July 8 |
|
Millstream Dr. |
Amber Dr. |
Hayward Rd. |
July 9 |
July 10 |
#####