| Revised: 06/06//07 | |||||||||
| City of Frederick | |||||||||
| 2007 (Balance = 43,433 GPD) | |||||||||
| Non-Residential Water and Sewer Allocation Master List | |||||||||
| THIS NON-RESIDENTIAL WATER AND SEWER ALLOCATION MASTER LIST IS PRELIMINARY AND ANY ALLOCATION PROPOSALS WITHIN THIS DRAFT ARE PRELIMINARY AND DO NOT CONVEY, VEST OR GUARANTEE ANY ALLOCATION AND SHOULD NOT BE CONSTRUED AS SUCH. | |||||||||
| Tier 1 | |||||||||
| Project Status-Existing buildings, including shell structures, vacant or partially vacant buildings with insufficient interior plumbing for the use(s) within the building(s), provided the total water demand does not exceed the Final Allocation as defined in Subsection E of the Water and Sewer Allocation Ordinance | |||||||||
| (Next Step in Approval Process-Apply and Receive Building Permit for Installation of Plumbing Fixtures/Water) | |||||||||
| Project Name | Contact Name | Permit # | Total Project Area (SF) | Notes | Maximum Potential Water and Sewer Demand by Project (GPD) | Water and Sewer Allocated to date to Project (GPD) | Remaining Potential Water and Sewer Demand by Project (GPD) | ||
| 1 | 406 N. Market Street | Chris Weaver | 984 sf | Office to Salon | 345 | 345 | 0 | ||
| 2 | 58 South Carrol Street (B& O Depot) | Mike Wiley | 800 sf (50 Seats) | Depot to Restaurant | 1,210 | 1,210 | 0 | ||
| 3 | 246 E. 6th Street | Kelly Chapin | 1,382 sf gross (788 sf salon) | Office to Salon (138 credit) | 138 | 138 | 0 | ||
| 4 | 620 West Patrick Street | Bill Pompeii | 1,020 sf gross | SF to office/Apt | 32 | 32 | 0 | ||
| 5 | 407 N. Market Street | Jean Loius Lepage | 528 sf gross | Attic Space to Office | 53 | 53 | 0 | ||
| 6 | 405 W 7th Street | Kevin Crawly | 6,000 sf gross | Medical Office to Rest./Dialysis Facility | 5,352 | 5,352 | 0 | ||
| Total by Tier (GPD) | 8,502 | 7,501 | 0 | ||||||
| *Cumulative Total (GPD) | 8,502 | 7,501 | 0 | ||||||
| Tier 2 | |||||||||
| Project Status-Projects with building construction drawing approval, and Final Site Plan (with existing recorded lot) approval, with all conditions met, and off-site public improvements bonded, under construction or completed and on-site improvements approved by City Engineer. | |||||||||
| (Next Step in Approval Process-Need to Apply and Receive Building and Site Related Permit for Construction, including Installation of Plumbing Fixtures/Water) | |||||||||
| Project Name | Contact Name | Date of Unconditional Site Plan Approval | Date Building Construction Drawings Approved | Net Acres | Maximum Potential Water and Sewer Demand by Project (GPD) | Water and Sewer Allocated to date to Project (GPD) | Remaining Potential Water and Sewer Demand by Project (GPD) | ||
| 1 | 0 | ||||||||
| Total by Tier (GPD) | |||||||||
| *Cumulative Total (GPD) | |||||||||
| Tier 3 | |||||||||
| Project Status-Site Plan, with all conditions met, and Final Plat, consistent with the Site Plan and with all conditions met, with off-site public improvements bonded, under construction, or completed and engineering improvement plans approved/signed by City Engineer. | |||||||||
| (Next Step in Approval Process-Final Plat must be recorded, Need to Apply and Receive Building and Site Related Permit for Construction, including Installation of Plumbing Fixtures/Water) | |||||||||
| Project Name | Contact Name | Date of Unconditional Site Plan Approval | Date of Improvement Plan Approval | Net Acres | Maximum Potential Water and Sewer Demand by Project (GPD) | Water and Sewer Allocated to date to Project (GPD) | Remaining Potential Water and Sewer Demand by Project (GPD) | ||
| 1 | 0 | ||||||||
| Total by Tier (GPD) | 0 | 0 | 0 | ||||||
| *Cumulative Total (GPD) | 0 | 0 | 0 | ||||||
| Tier 4 | |||||||||
| Project Status-Final Site Plan, with all conditions met, and Final Plat, consistent with the Site Plan and with all conditions met, without approved improvement plans (on-site or off-site) | |||||||||
| (Next Step in Approval Process- Need Engineering approval of Improvement Plans, Final Plat must be recorded, Need to Apply and Receive Building and Site Related Permit for Construction, including Installation of Plumbing Fixtures/Water) | |||||||||
| Project Name | Contact Name | Date of Unconditional Site Plan Approval | Net Acres | Notes | Maximum Potential Water and Sewer Demand by Project (GPD) | Water and Sewer Allocated to date to Project (GPD) | Remaining Potential Water and Sewer Demand by Project (GPD) | ||
| 1 | Carroll Creek Galleria - Site D | Ed Wormald | Lot of Record | 2.6 | Requires Site Plan | 4,680 | 517 | 4,163 | |
| Total by Tier (GPD) | 4,680 | 517 | 4,163 | ||||||
| *Cumulative Total (GPD) | 12,271 | 12,271 | 12,272 | ||||||
| Tier 5 | |||||||||
| Project Status-Proposed projects that do not have Site Plan, with all conditions met. These projects are not eligible for a water allocation. | |||||||||
| (Next Step in Approval Process-Must obtain Site Plan approval with all conditions met before becoming eligible for allocation, Need Engineering approval of Improvement Plans, Final Plat must be recorded, Need to Apply and Receive Building and Site Related Permit for Construction, including Installation of Plumbing Fixtures/Water) | |||||||||
| Project Name | Contact Name | Date of Unconditional PSU Plan Approval | Net Acres | Notes | Maximum Potential Water and Sewer Demand by Project (GPD) | Water and Sewer Allocated to date to Project (GPD) | Remaining Potential Water and Sewer Demand by Project (GPD) | ||
| 1 | 104-106 N. Market Street | David and Sonia Demiray | N/A | Apt/Retail to Office/Storage/Market/Apt | 1,372 | 371 | 521 | ||
| 2 | Ballenger Creek Center PND-Lot 4 | LSA | 11/30/2004 | 4.16 | Requires Site Plan | 3,744 | 0 | 3,744 | |
| 3 | Ballenger Creek Center PND-Lot 5R | LSA | 11/30/2004 | 44.06 | Requires Site Plans/Plats | 59,481 | 20,520 | 38,961 | |
| 4 | Barricks B | LSA | Lot of Record | 2.65 | Requires Site Plan | 4,770 | 4,770 | ||
| 5 | Frederick Airport Park, Lot 1 | Anne Rollins | 7/9/2001 | 8 | Requires Site Plan | 7,200 | 4,407 | 2,793 | |
| 6 | Frederick Airport Park, Lot 2 | Anne Rollins | 7/9/2001 | 9.95 | Requires Site Plan | 8,955 | 3,879 | 5,076 | |
| 7 | Frederick Airport Park, Lot 3 | Anne Rollins | 7/9/2001 | 9.09 | Requires Site Plan | 8,181 | 0 | 8,181 | |
| 8 | Frederick Airport Park, Lot 4 | Anne Rollins | 7/9/2001 | 7.69 | Requires Site Plan | 6,921 | 0 | 6,921 | |
| 9 | Frederick Airport Park, Lot 5 | Anne Rollins | 7/9/2001 | 9.15 | Requires Site Plan | 8,235 | 0 | 8,235 | |
| 10 | Frederick Airport Park, Lot 6 | Anne Rollins | 7/9/2001 | 4.7 | Requires Site Plan | 4,230 | 0 | 4,230 | |
| 11 | Frederick Airport Park, Lot 7 | Anne Rollins | 7/9/2001 | 7.03 | Requires Site Plan | 6,327 | 0 | 6,327 | |
| 12 | Frederick Airport Park, Lot 8 | Jacques Pare' | 7/9/2001 | 13.5 | Final Site Plan Approved/Requires Site Plan | 12,222 | 4,186 | 8,036 | |
| 13 | Frederick Airport Park, Lot 15 | Anne Rollins | 7/9/2001 | 31.69 | Requires Site Plan | 28,521 | 0 | 28,521 | |
| 14 | Industrial Center East Lots 217 | Ed Scott | 11/8/2001 | 1.042 | Requires Site Plan | 938 | 541 | 397 | |
| 15 | Industrial Center East Lots 218 | Ed Scott | 11/8/2001 | 1.023 | Requires Site Plan | 921 | 531 | 390 | |
| 16 | Industrial Center East Lots 219 | Ed Scott | 11/8/2001 | 1.178 | Requires Site Plan | 1,060 | 612 | 448 | |
| 17 | Industrial Center East Lots 220 | Ed Scott | 11/8/2001 | 1.649 | Requires Site Plan | 1,484 | 856 | 628 | |
| 18 | Industrial Center East Lots 224 | Ed Scott | 11/8/2001 | 1.376 | Requires Site Plans/Plats | 1,238 | 1,500 | -262 | |
| 19 | Industrial Center East Lots 330 | Ed Scott | 11/9/2001 | 7.88 | Final Site Plan Approved | 7,092 | 4,000 | 3,092 | |
| 20 | Industrial Center East Lots 334 | Ed Scott | 11/8/2001 | 2.433 | Requires Site Plans/Plats | 2,190 | 1,263[1] | 927 | |
| 21 | Industrial Center East Lots 335 | Ed Scott | 11/8/2001 | 2.392 | Final Site Plan Approved | 2,153 | 784 | 1,369 | |
| 22 | Industrial Center East Lots 336 | Ed Scott | 11/8/2001 | 2.35 | Final Site Plan Approved | 2,115 | 927 | 1,188 | |
| 23 | Industrial Center East Lots 337 | Ed Scott | 11/8/2001 | 2.135 | Requires Site Plans/Plats | 1,922 | 1,263[2] | 659 | |
| 24 | Industrial Center East Lots 338 | Ed Scott | 11/8/2001 | 2.1 | Requires Site Plans/Plats | 1,890 | 1,263[3] | 627 | |
| 25 | Hargett Farm PND-Commercial | Jonathon Soule | 11/15/2004 | 2.9 | Requires Site Plans/Plats | 5,220 | 0 | 5,220 | |
| 26 | Riverside Corporate Park-West Lot 102 | Chris Kline | 5/30/2001 | 3.55 | Requires Site Plans | 3,195 | 3,129 | 66 | |
| 27 | Riverside Corporate Park-West Lot 103 | Chris Kline | 5/30/2001 | 1.77 | Requires Site Plans | 1,593 | 1,560 | 33 | |
| 28 | Riverside Corporate Park-West Lot 104 | Chris Kline | 5/30/2001 | 1.47 | Requires Site Plans | 1,323 | 1,089 | 234 | |
| 29 | Riverside Corporate Park-West Lot 105 | Chris Kline | 5/30/2001 | 3.46 | Requires Site Plans | 3,114 | 2,564 | 550 | |
| 30 | Riverside Corporate Park-West Lot 107 | Chris Kline | 5/30/2001 | 3.54 | Final Site Plan Approved | 3,186 | 1,800 | 1,386 | |
| 31 | Riverside Corporate Park-West Lot 110 | Chris Kline | 6/2/2001 | 13.38 | Final Site Plan Approved | 12,042 | 8,000 | 4,042 | |
| 32 | Riverside Corporate Park-West Lot 113 | Chris Kline | 6/5/2001 | 11.627 | Final Site Plan Approved | 10,464 | 10,246 | 218 | |
| 33 | Riverside Corporate Park-West Lot 114 | Chris Kline | 6/6/2001 | 4.53 | Requires Site Plans | 4,077 | 3,992 | 85 | |
| 34 | Riverside Corporate Park-West Lot 115 | Chris Kline | 6/7/2001 | 7.598 | Final Site Plan Approved | 6,838 | 1,800 | 5,038 | |
| 35 | Riverside Corporate Park-West Lot 116 | Chris Kline | 6/8/2001 | 2.26 | Requires Site Plans | 2,034 | 1,674 | 360 | |
| 36 | Riverside Corporate Park Lots 258 | Steve Chafitz | 7/9/2001 | 11.21 | Final Site Plan Approved | 10,089 | 8,098 | 1,991 | |
| 37 | Riverside Corporate Park Lots 257 | Steve Chafitz | 7/9/2001 | 7.089 | Final Site Plan Approved | 6,380 | 9,566 | -3,186 | |
| 38 | Riverside Corporate Park Lot 401 | Steve Chafitz | 7/9/2001 | 9.99 | Requires Site Plans | 8,991 | 0 | 8,991 | |
| 39 | Riverside Corporate Park Lot 402 | Steve Chafitz | 7/9/2001 | 15.67 | Requires Site Plans | 14,103 | 0 | 14,103 | |
| 40 | Riverside Corporate Park Lot 403 | Steve Chafitz | 7/9/2001 | 7.4 | Requires Site Plans | 6,660 | 0 | 6,660 | |
| 41 | Riverside Corporate Park Lot 404 | Steve Chafitz | 7/9/2001 | 6.7 | Requires Site Plans | 6,030 | 0 | 6,030 | |
| 42 | Riverside Corporate Park Lot 405 | Steve Chafitz | 7/9/2001 | 6.7 | Requires Site Plans | 6,030 | 0 | 6,030 | |
| 43 | Riverside Corporate Park Lot 406 | Steve Chafitz | 7/9/2001 | 7.3 | Requires Site Plans | 6,570 | 0 | 6,570 | |
| 44 | Riverside Corporate Park Lot 407A | Steve Chafitz | 7/9/2001 | 7 | Final Site Plan Approved | 6,300 | 0 | 6,300 | |
| 45 | Riverside Corporate Park Lot 407B | Steve Chafitz | 7/9/2001 | 6.67 | Requires Site Plans | 6,003 | 0 | 6,003 | |
| 46 | Riverside Corporate Park Lot 408 | Steve Chafitz | 7/9/2001 | 8.9 | Requires Site Plans | 8,010 | 0 | 8,010 | |
| 47 | Riverside Corporate Park Lot 409 | Steve Chafitz | 7/9/2001 | 7.7 | Requires Site Plans | 6,930 | 0 | 6,930 | |
| 48 | Riverside Corporate Park Lot 410 | Steve Chafitz | 7/9/2001 | 16 | Requires Site Plans | 14,400 | 0 | 14,400 | |
| 49 | Riverside Corporate Park Lot 411 | Steve Chafitz | 7/9/2001 | 8.2 | Requires Site Plans | 7,380 | 0 | 7,380 | |
| 50 | Riverside Corporate Park Lot 412 | Steve Chafitz | 7/9/2001 | 8.3 | Requires Site Plans | 7,470 | 0 | 7,470 | |
| 51 | Riverside Corporate Park Lot 413 | Steve Chafitz | 7/9/2001 | 6.5 | Requires Site Plans | 5,850 | 0 | 5,850 | |
| 52 | Swami-Nathan Property | Anne Rollins | Lot of Record | 93.93 | Requires Site Plans | 84,537 | 0 | 84,537 | |
| 53 | TJ Self Storage | Bruff Proctor | Lot of Record | 6.39 | PC Approved Site Plan | 8,627 | 0 | 8,627 | |
| 54 | Rentals Unlimited | Lot of Record | 5.23 | PC Approved Site Plan | 7,060 | 0 | 7,060 | ||
| 55 | Village Square | Thomas Lynch | Lot of Record | 3.2 | Requires Site Plans | 5,760 | 0 | 5,760 | |
| 56 | Wormald Development Company Monocacy Blvd. | Ed Wormald | Lot of Record | 15.0175 | Require Site Plan | 13,515 | 0 | 13,515 | |
| 57 | Worman's Mill Mill Island Parkway | Robert Wormald | 1999 | 1.49 | Requires Site Plans/Plats | 1,341 | 0 | 1,341 | |
| 58 | Worman's Mill Town Square Center | Robert Wormald | 1987/1988 | 0.33 | Requires Site Plans/Plats | 297 | 0 | 297 | |
| 59 | Triangle Motors | Tom Meachem | 6 | Require Site Plan | 8,100 | 0 | 8,100 | ||
| 60 | Northgate (West of Route 15, East of TJ Drive) | Robert Love | 52 | Requires Preliminary Subdivision Plan/Site Plans/Plats | 46,800 | 0 | 46,800 | ||
| 61 | Park Hall (1100 East Patrick St.) | Ted McCutcheon | 3.96 | Require Site Plan | 7,128 | 0 | 7,128 | ||
| 62 | Park Hall Back Lot (Behind 1100 East Patrick St.) | Ted McCutcheon | 1.53 | Require Site Plan | 2,754 | 0 | 2,754 | ||
| 63 | 1040 West Patrick Street | Gary Mullins | 2.5 | Require Site Plan | 4,500 | 0 | 4,500 | ||
| 64 | Bentztowne Condominiums | Galen Clagett | 0.5 | Require Site Plan | 900 | 0 | 900 | ||
| 65 | Market Square Commercial | Galen Clagett | 49.205 | Requires Preliminary Subdivision Plan/Site Plans/Plats | 44,285 | 0 | 44,285 | ||
| 66 | Dewey Jordan, Inc. | Ted McCutcheon | 4.44 | Require Site Plan | 7,992 | 0 | 7,992 | ||
| 67 | Lizas Site (South Side/U.S. Route 40 | Rania Lizas | 2.02 | Require Site Plan | 3,636 | 0 | 3,636 | ||
| TOTAL | 605,559 | 100,050 | 505,509 | ||||||
| ** | Total Gallons Per Day (GPD) Calculated Per Page #630 of the City's Land Management Code (LMC) Water and Sewer Allocation Ordinance (4.99 acres or less of land = 1,800 GPD per acre; and between 5 and 19.99 acres of land = 1,350 GPD; and 20 acres or more of land = 900 GPD per Acre) | ||||||||
| *** | All Numbers are Subject to Change | ||||||||