Chapter 5 BUILDINGS*
ARTICLE III. ADMINISTRATION
Sec. 5-23. Certificates of occupancy.
(a) A certificate of occupancy, indicating compliance with permits and
construction documents, shall be obtained prior to occupancy of a building in
the following cases:
(1) Erection of a new building;
(2) Erection of an
addition to a building; or
(3) Change of use and occupancy classification as
set forth in the building code.
(b) Upon completion and approval of all
required final inspection(s) the code official shall issue a certificate of
occupancy. The certificate of occupancy shall be available for inspection by the
code official at any reasonable time.
(c) The certificate of occupancy shall
bear the signature of the code official and specify the following:
(1) The
address of the building;
(2) The location within the building if for part of
a building;
(3) The edition of the code under which the certificate is
issued;
(4) The occupancy and ueG group in accordance with the building
code;
(5) The type of construction as defined by the building
code;
(6) If and where an automatic sprinkler system is provided and whether
it is required;
(7) If a standpipe system is provided and whether it is
required;
(8) Any variances or special conditions; and
(9) The permit
number.
(d) Upon request of the applicant, a temporary or partial
certificate of occupancy may be issued to occupy the premises or a portion of
the premises before completion of the entire work or operation covered by the
permit provided that such portion or portions will be occupied safely prior to
full completion of the structure or installation of equipment and systems
without endangering life or public welfare. Such issuance shall be in accordance
with departmental procedures and the code official shall notify the applicant of
any limitations or restrictions imposed by the partial or temporary
occupancy.
(e) Any outstanding fees shall be paid prior to the issuance of
the certificate of occupancy. (Ord. No. G-05-18, § 13, 12-19-05)