Sec. 4-15. Building permits.


(a) Required certificates. A developer may not apply for a building permit for the construction of a project unless the project has first been issued, or deemed exempt from, each of the following certificates:
(1) Certificate of adequate public facilities-water line capacity;
(2) Certificate of adequate public facilities-sewer line capacity;
(3) Certificate of adequate public facilities-roads;
(4) Certificate of adequate public facilities-schools;
(5) Certificate of adequate public facilities-public water treatment; and
(6) Certificate of adequate public facilities-sewer basin treatment.
(b) Fees. The city may not accept any application for a building permit until all fees required pursuant to this chapter have been paid. (Ord. No. G-07-6, § 1, 3-22-07; Ord. No. G-07-19, § 1, 9-6-07)