Chapter 4 ADEQUATE PUBLIC FACILITIES
ARTICLE II. CERTIFICATES OF ADEQUATE PUBLIC FACILITIES
Sec. 4-15. Building permits.
(a) Required certificates. A developer may not apply for a
building permit for the construction of a project unless the project has first
been issued, or deemed exempt from, each of the following
certificates:
(1) Certificate of adequate public facilities-water line
capacity;
(2) Certificate of adequate public facilities-sewer line
capacity;
(3) Certificate of adequate public
facilities-roads;
(4) Certificate of adequate public
facilities-schools;
(5) Certificate of adequate public
facilities-public water treatment; and
(6) Certificate of adequate
public facilities-sewer basin treatment.
(b) Fees. The city may not
accept any application for a building permit until all fees required pursuant to
this chapter have been paid. (Ord. No. G-07-6, § 1, 3-22-07; Ord. No.
G-07-19, § 1, 9-6-07)